Weekly Goals
Week | End of Week Goals |
---|
July 5 - 11 | Chassis: (All done!) Access to Welding Room Finish sanding & assembling jigs (done) Drop off parts for welding Assembly more jigs Welding components onto Chassis
Aero: (Bleeding into week of July 12 - due to booking conflicts with Waterloop) Battery Box: |
July 12 - 18 | Chassis: Pick up waterjet parts - End of the week Sand chassis, assemble more jigs
Schedule welding in E5 - welding components onto Chassis
Aero: Finish prepping side panel molds - end of the week
Begin material prep for side panels layup
Make a decision if we want to layup both - yes to both
finish side panel molds 3, 4
b bulkheads sand, potentially make blank and machine second mold as well (based on SDC)
Composites: |
July 19 - 25 | Chassis: Pick up waterjet parts - Early this week Submit work request and drop off parts at E3 Sand chassis and (maybe) tack weld seatbelt mounts(Saturday)
Aero: visit cold storage to pick up adhesive film
chassis measurements for b-bulkhead layup on thursdayThursday mold release on side panel 1 and 2 connect the molds (molds are misaligned) material prep (nomex, vacuum bag, breather cloth, peel ply),
pick up kerosene
trim carbon fibre and adhesive film
Composites: Battery Box: Purchases: |
July 26 - Aug 1 | Chassis: |
| |