Week

End of Week Goals

July 5 - 11

Chassis: (All done!)

  • Access to Welding Room

  • Finish sanding & assembling jigs (done)

  • Drop off parts for welding

  • Assembly more jigs

  • Welding components onto Chassis

Aero: (Bleeding into week of July 12 - due to booking conflicts with Waterloop)

  • Side Panel Molds ready by the end of this week for layup

Battery Box:

  • Continue module manufacturing

July 12 - 18

Chassis:

  • Pick up waterjet parts - End of the week

  • Sand chassis, assemble more jigs

  • Schedule welding in E5 - welding components onto Chassis

    • Clamping tubes prior to welding

Aero:

  • Finish prepping side panel molds - end of the week

  • Begin material prep for side panels layup

    • blocked by no driver - see if we have a driver???

    • drawings are ready

  • Make a decision if we want to layup both - offlineyes to both

  • finish side panel molds 3, 4

  • b bulkheads sand, potentially make blank and machine second mold as well (based on SDC)

    • first b-bulkhead sanded

    • second b-bulkhead - in progress

Composites:

  • infusion testing Saturday

  • Double check prep work for the infusion testing session (Friday)

    • use mold release/PVA, don’t apply Loctite

July 19 - 25

July 26 - Aug 1

...