W21 Term Goals

  • Assembling final versions of boards

  • Motor Sense Validation (Hall-effect issues) - Weekend :)

  • High voltage testing 

  • Cell balancing + BMS Testing - in progress

  • Validation for final versions of boards (FW & HW)

  • Harnessing Planning ??

...

  • Harnessing and Locations in the vehicle

    • Will block

  • Enclosures

    • Wiring, enclosure design, wiring, cable management have not been decided

    • Impacted by Dash Team

  • Aerobody

    • Blocks electrical wiring

  • Catamaran Box

    • Blocks enclosures (Rear electronics)

Hardware Working Sessions

  • Elec only: 9AM - 3PM on Saturdays (may be changed due to Mech, we’ll know the Wednesday of)

  • Can also go in during the week (smile)

Task Breakdown

Details

Goals + Timeframe

Status

Assembling final versions of boards (HW)

  • PD

    Status
    colourYellow
    titleValidation

  • PS

    Status
    colourGreen
    titleAssembled

  • Steering

  • Lights

    Status
    colourYellow
    titleAssembly in progress

  • Solar

    Status
    colourRed
    titleJuly

  • UV Cutoff (Rev 1)

  • Centre Console

  • Set a timeslot every weekend, 4-5 hardware members/leads

    • 1-2 big board completions

    • 4 hours/slot w/multiple people, Sat 9AM-2PM slot (?), 3 weeks

    End of March

    • Status
      colourRed
      titleJune 29

    • Centre Console

      Status
      colourRed
      titleJune 28

    Need to do more testing for lights (DRLs get hot)

    Determine if we have a good enough final version for each boards. (If not, we’ll put together a new rev for board sendout before the Fall term)

    Current Sense:

    Status
    colourYellow
    titleIn Progress

    Center Console

    Status
    colourYellow
    titleIn Progress

    Board Validation

    (see tracker for validation priorities)

    Charger validation → July 10th work session

    Telemetry

    Hardware x Firmware meeting to discuss current state

    Collect equipment in Waterloo, make purchases

    Motor Sense Validation (HW)

    • At the stage of integrating Sense to Controllers

    • Blocks all of Power Train

    Starting this weekend (Mar 6) - 9 AM - 11 AM

    End of March

    Done as much as we can do, as of W21

    Status
    colourGreen
    titleDone

    for now

    High voltage testing (HW)

    • Integration Testing

    • Charging

    • Battery

    • Blocked by Motor Sense Validation

    • Blocked by Pre-Charge integration testing

    Precharge needs to be tested with motor

    Cell balancing + BMS Testing (FW)

    • Need to test passive balancing

    • 1 AFE is broken

    End of March

    Status
    colourYellow
    titleMedium

    Updating Firmware (FW) - Remote

    • Updating FW for new boards

    Complete before HW is assembled

    More detailed planning to follow

    Validation for final versions of boards (FW)

    • Priority list for validation has been provided

    • Testing as boards are assembled

    • Charger

    • Solar

    End of AprilSpring Term

    Solar Validation

    • Blocked by solar sense assembly

    End of May 

    Harnessing Planning

    • Fully remote

    End of APrilNext term


    Issues with commitment……...

    ...

    Long Term Planning

    Canadian Open: June 2022
    Competition: July 2022

    Not feasible:

    • No major design changes or architectural changes

    Spring 2021

    • Begin rear electronics integration

    • Begin harnessing (majority)

    • Begin Enclosure bring up, mounting boards

    • BMS, Full Mockup End of Spring

    • + Charging, lights, displays Integration for mockup

    • + Solar Testing


    Fall 2021

    • Solar Integration

    • Integration

      • All Mockup Items

      • Telemetry

      • CAN Network complete

    • BMS Validation

      • How long till we can start testing with the battery pack → end of spring term (may be able to test w/ cells on the bench, but we’ll want to test with the BMS with battery before integration with mech)

    • BPS Scrutineering Mock-test


    Winter 2022

    • Testing


    Spring 2022 (May)

    • Testing for competition


    Topics of Discussion:

    • Key Milestones

      • BMS Mockup

      • Full Mockup

      • Charging, Lights

      • Solar

    • Testing

    • Integration


    Other Projects Post-Completion