Project | Goal | OG Date | Date (March) | Priority | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months | 3 months End of May |
| ||||||||||||||||||
Seats | Complete manufacturing
| 2 months | 2 Months End of JulyAugust |
| ||||||||||||||||||
Doors | Complete FULL manufacturing plan (EOT W21)
** Any Structures changes to hinges need to be communicated | 2 months | Manufacturing Time: 2 months Commitment for Manufacturing Completion: Mid-F21 |
| ||||||||||||||||||
Trim | Complete detailed design
| 4 months
Complete Fall Term Trim Integration: EOT W22Trim Integration: 2 months |
| |||||||||||||||||||
Dashboard | Complete detailed design | 4 months Manufacturing: 3 months Integration: 1-2 months |
| Displays | 2 months |
“easiest” |
|
Manufacturing Projects
Note |
---|
Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. Strongly recommend we do this asap so that we don’t run into problems when it’s too lateVDR is in progress for seats (~75% completed). |
Project | Task | Time Allocation | Status | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT | ||||||||
Catamaran Cover | Manufacture Molds
| 2 weeks |
| ||||||||
Manufacture Major Battery Box Panels (bottom + side walls + lid)
| 3 weeks |
| |||||||||
Manufacture Internal Parts | 1 week |
| |||||||||
Material Testing
| 1 week |
| |||||||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week |
| |||||||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks |
| |||||||||
External Finish
| TBD |
| |||||||||
Seats | Seats Mock-up (optional) | 1 week |
| ||||||||
Manufacture Seats Flat Panels
• Bond
| 2 weeks + 1 week = 3 weeks |
| |||||||||
Ballast
| 2 weeks |
| |||||||||
Brackets and fastener installation
| 3 weeks |
| |||||||||
Manufacture Seatbacks | 2 weeks + 1 week = 3 weeks |
| |||||||||
Finishing Touches | TBD |
|
Integration with Subteams/Dependencies
Catamaran depends on:
Aero-chassis BP integration
Battery box modules ready
Dynamics assembly
Seats depends on:
Chassis integrationBottom
Side panel + chassis integrationintegration (for rear seats install)
Floor panels SHOULD NOT need to be added into the vehicle (so that brackets can be welded)
Welding items for chassis
B,C-bulkheads Integrated
Dashboard depends on:
Dynamics
Aero-Chassis Integration (A-bulkhead, A-Plane)
Interior doors
Electrical & Battery Box need to be integrated so we can route wires
Depends on Displays & cameras to be ready
...
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Kristen (Co-op) | • Assisting with manufacturing | On-site |
Sheila (SchoolCo-op)) | • Leading manufacturing of seats | On-site |
Cordelia (SchoolCo-op) | • PM for dashboard | On-site for Spring |
Asher (Co-op) | • Leading manufacturing of seats | On-site |
Kimia (Co-op) | • Design of ballast | Remote |
Lovisa (Co-op) | • PM of trim | Remote |
Joy (School) | • Assisting with manufacturing | On-Site |
Geoffrey (Co-op) | • Form factoring of trim | Remote |
...