Meeting Agenda:
1.a Most collisions outside of ASC, explicit dynamic analysis makes the most sense Matt said - the way the load was worded → “5G” instead of a speed. A lot of teams chose to do that instead of dynamics analysis. Therefore static analysis was the easiest was to pass ASC. 1.b Mass Analysis
Action Items:
Night of Tuesday, May 18 - Min finishes Mass Analysis Study Tuesday/Wednesday May 18/19 - Review Mass Analysis Simulations with Tommy + Create small report for Mech Advisors (Leif, Matt, and Kevin + Catherine) to review and approve Thursday, May 20 - Begin Stage 2 deliverables (assuming stress values are still not solved Saturday, May 22 - Have mech-leads meeting to review progress and give training on Stage 2 deliverables Night of Tuesday, May 25 - Finish Stage 2 deliverables Tuesday/Wednesday May 25/26 - Review Stage 2 deliverables + Create small report for Mech Advisors (Leif, Matt, and Kevin + Catherine) to review and approve May 31 - Complete Supplier Interfacing Logistics for approved solution |
2021.05.22