Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Expand

Last updated: May 6, 2021

Legend:

  • Red = High Priority

  • Purple = Medium Priority

  • Yellow = Low Priority

Comments:

  • Timeline - depends on school and work term report

  • Sounds like we are on decent ground; not the ideal case, but ok

  • Likely that we will need a third week

No.

Project Stage

Due Date

Status

Blocked By

1

Simulation Use and Setup Justification

May 12th

In ProgressDone

2

Simulation Studies and Effect of Mass Analysis

May 12th19th

In Progress

3

PVDR Feedback

May 20th

Not Started

6

4

Chassis Post-Welding Analysis

May 20th26th

Not Started

1, 2

5

Effect of Welding on the Properties of Tubes and Adhesives

May 20th

Not Started

6

6

Composite Solutions for Structural Reinforcement

May 20th27th

Not Started

1, 2

7

Review with Mech Advisors

May 28th

TBD

4, 6

Structural FEA & Reinforcements (Overall Project)

May 20th (for momentum and contingency)

In Progress

Structural FEA & Reinforcements (Overall Project)

End of May (Hard Due Date)

In Progress

...