Last updated: May 6, 2021 Legend: Red = High Priority Purple = Medium Priority Yellow = Low Priority
Comments: Timeline - depends on school and work term report Sounds like we are on decent ground; not the ideal case, but ok Likely that we will need a third week
No. | Project Stage | Due Date | Status | Blocked By |
---|
1 | Simulation Use and Setup Justification | May 12th | In ProgressDone | | 2 | Simulation Studies and Effect of Mass Analysis | May 12th19th | In Progress | | 3 | PVDR Feedback | May 20th | Not Started | 6 | 4 | Chassis Post-Welding Analysis | May 20th26th | Not Started | 1, 2 | 5 | Effect of Welding on the Properties of Tubes and Adhesives | May 20th | Not Started | 6 | 6 | Composite Solutions for Structural Reinforcement | May 20th27th | Not Started | 1, 2 | 7 | Review with Mech Advisors | May 28th | TBD | 4, 6 | | Structural FEA & Reinforcements (Overall Project) | May 20th (for momentum and contingency) | In Progress | | | Structural FEA & Reinforcements (Overall Project) | End of May (Hard Due Date) | In Progress | |
|