Last updated: May 3, 2021 (7:00 PM EST) Project Stage | Due Date | Status | Blocked By |
---|
Simulation Use and Setup Justification | | Not Started | | Simulation Studies and Effect of Mass Analysis | | Not Started | | PVDR Feedback | | Not Started | | Chassis Post-Welding Analysis | | Not Started | | Effect of Welding on the Properties of Tubes and Adhesives | | Not Started | | Composite Solutions for Structural Reinforcement | | Not Started | | Structural FEA & Reinforcements (Overall Project) | May 20th (for momentum and contingency) | In Progress | | Structural FEA & Reinforcements (Overall Project) | End of May (Hard Due Date) | In Progress | |
|