This document outlines the tasks for the Interiors team for the Winter 2021 term.
Term Goals
Project | Goal | OG Date | Date (March) | Priority | ||||||
---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months | 2 months End of April |
| ||||||
Seats | Complete manufacturing
| 2 months | 2 Months |
| ||||||
Doors | Complete manufacturing plan ** Any Structures changes to hinges need to be communicated | 2 months | 2 Months |
| ||||||
Trim | Complete detailed design | 4 months |
| |||||||
Dashboard | Complete detailed design | 4 months |
| |||||||
Displays | Ensure Infotainment display works | 2 months | 4 months End of April |
“easiest” |
...
Project | Task | Time Allocation | Status | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT | |||||||
Catamaran Cover | Install catamaran items on bottom panel + chassis | 2 weeks |
| |||||||
Manufacture Major Battery Box Panels (bottom + side walls + lid) | 3 weeks |
| ||||||||
Manufacture Internal Parts |
| |||||||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week |
| ||||||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks |
| ||||||||
External Finish
| TBD |
| ||||||||
Seats | Seats Mock-up (optional) | 1 week |
| |||||||
Manufacture Seats Flat Panels | 2 weeks |
| ||||||||
Manufacture Seatbacks | 2 weeks |
| ||||||||
Finishing Touches | TBD |
|
Contingency Planning
If lockdown happens, manufacturing will be impacted by as long as lockdown remains
Design Projects (Trim + Dashboard)
Task | Time Allocation | Status | ||||||
---|---|---|---|---|---|---|---|---|
Finalize Research + Concepting | 2 weeks |
| ||||||
CAD design | 4 weeks |
| ||||||
Materials Selection | 2 weeks |
| ||||||
Supplier Interfacing Assembly Plan | TBD |
|
Core Team
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Kristen (Co-op) | • Assisting with manufacturing | On-site |
Sheila (School) | • Leading manufacturing of seats | On-site |
Cordelia (School) | • PM for dashboard | Remote |
Lovisa (Co-op) | • PM of trim | Remote |
Joy (School) | • Assisting with manufacturing | On-Site |
Geoffrey (Co-op) | • Form factoring of trim | Remote |
...