Note |
---|
Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. Strongly recommend we do this asap so that we don’t run into problems when it’s too late. |
Project | Task | Time Allocation | Status | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT | |||||||
Catamaran Cover | Install catamaran items on bottom panel + chassis | 2 weeks |
| |||||||
Manufacture Major Battery Box Panels (bottom + side walls + lid) | 3 weeks |
| ||||||||
Manufacture Internal Parts |
| |||||||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week |
| ||||||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks |
| ||||||||
External Finish
| TBD |
| ||||||||
Seats | Seats Mock-up (optional) | 1 week |
| |||||||
Manufacture Seats Flat Panels | 2 weeks |
| ||||||||
Manufacture Seatbacks | 2 weeks |
| ||||||||
Finishing Touches | TBD |
|
...