Project | Goal | Date | Priority | ||||||
---|---|---|---|---|---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months |
| ||||||
Seats | Complete manufacturing
| 2 months |
| ||||||
Doors | Complete manufacturing plan ** Any Structures changes to hinges need to be communicated | 2 months |
| ||||||
Trim | Complete detailed design | 4 months |
| ||||||
Dashboard | Complete detailed design | 4 months |
| ||||||
Displays | Ensure Infotainment display works | 2 months |
“easiest” |
Manufacturing Projects
Project | Task | Time Allocation | |||
---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT | |||
Catamaran Cover | Install catamaran items on bottom panel + chassis | 2 weeks | |||
Manufacture Major Battery Box Panels (bottom + side walls + lid) | 3 weeks | ||||
Manufacture Internal Parts | |||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week | ||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks | ||||
External Finish
| TBD | ||||
Seats | Seats Mock-up (optional) | 1 week | |||
Manufacture Seats Flat Panels | 2 weeks | ||||
Manufacture Seatbacks | 2 weeks | ||||
Finishing Touches | TBD |
Contingency Planning
If lockdown happens, manufacturing will be impacted by as long as lockdown remains
Design Projects (Trim + Dashboard)
...