Project | Task | Time Allocation | |||
---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT | |||
Catamaran Cover | Install catamaran items on bottom panel + chassis | 2 weeks | |||
Manufacture Major Battery Box Panels (bottom + side walls of box+ lid) | 3 weeks | ||||
Manufacture Flat Panels | |||||
Assembly of battery box panels | 2 weeks | ||||
Mount Latches | 1 week | ||||
Manufacturing Misc. (Components that go into the battery box) | |||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week | ||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks | ||||
External Finish
| TBD | ||||
Seats | Seats Mock-up (optional) | 1 week | |||
Manufacture Seats Flat Panels | 2 weeks | ||||
Manufacture Seatbacks | 2 weeks | ||||
Finishing Touches | TBD |
...
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Kristen (Co-op) | • Assisting with manufacturing | On-site |
Sheila (School) | • Leading manufacturing of seats | On-site |
Cordelia (School) | • PM for dashboard | Remote |
Lovisa (SchoolCo-op) | • PM of trim | Remote |
Joy (School) | • Assisting with manufacturing | On-Site |
Geoffrey (Co-op) | • Form factoring of trim | Remote |
...